Tuesday, February 26, 2008

Engineer's Report!

We finally have the much-awaited Engineer's Report for the slab fix.

As a result, we can now inspect the property and eventually pay the frame invoice ;)

We have an appointment with Kevin, our independent inspector, on Thursday 7:30am to inspect the frame/slab. Unfortunately though, our S/S is not sure whether he could make it that early ;)
We will do it, with or without him.

By the way, here are some photos of minor issues worth sharing:

hairline cracks to the garage:
CD79_BD41_220208_k

loose/no screws:
CD79_BD41_220208_p

CD79_BD41_220208_n

CD79_BD41_220208_o

Monday, February 25, 2008

Roof tiles delivered!

The roof tiles were delivered!

CD79_BD41_220208_q

more at the back:
CD79_BD41_220208_s

Wonder if they would start laying them while we're awaiting for the Engineer's Report on the slab fix.
Also, we haven't done the inspection yet.

Friday, February 22, 2008

Slab issues fixed

Calendar day 79 (working day 41):

Our issues with the slab were fixed!

Here are the before and after photos of the slab areas with overhang timber issue:

Right side of the entry door:
before:
CD65_BD31_080208_ex

taken from inside the house:
CD57_BD25_310108_dx

after:

CD79_BD41_220208_gx

CD79_BD41_220208_bx

Right side of the garage (front of mud room):
before:
CD65_BD31_080208_gx

taken from inside the house:
CD63_BD29_060208_tx

after:

CD79_BD41_220208_ix

Right side of the house (front of HT):
before:
CD65_BD31_080208_fx

after:

CD79_BD41_220208_fx

close-up shot:
CD79_BD41_220208_dx

Monday, February 18, 2008

Bulkhead to HT fixed!

Calendar day 75 (working day 37):

The issue to the bulkhead has finally been closed.
In order to retain the high 2340mm high doors to the HT area, we agreed to have the bulkhead to the HT entry smaller but doubled:

CD75_BD37_180208_dx

Tuesday, February 12, 2008

We have gutters/fascias and water pipes!

Works resumed today!

After Calendar day 69 (working day 33):

We now have gutters/fascias:
CD69_BD33_120208_ux

and water pipes connected to all wet areas:
CD69_BD33_120208_bx

laundry:
CD69_BD33_120208_fx

upper level ensuite and bathroom:
CD69_BD33_120208_kx

this is where the island bench would be:
CD69_BD33_120208_ix

we have basic (dumb) meter:
CD69_BD33_120208_tx

and have a look at the back of the fascia... i've always thought that the colour of the front and back are the same.. well, they're not:
CD69_BD33_120208_px

Monday, February 11, 2008

Issue resolved?

Our CSR informed us this afternoon that their engineering people thought of another option in order to address the issue with the high doors to HT without:
  • changing the 2340mm doors to smaller 2040mm doors, and
  • removing the bulkheads to the HT opening and rear Entry area.

The solution was to reduce the bulkhead from 300mm deep to 140mm deep and put in two beams instead of only one.

We were quite happy with that option and asked the CSR to email the full details of the change (with revised plans).

Building works stopped...

We were advised that building works has been stopped until the Home Theatre door issue is resolved.

When we visited the site in the afternoon, we saw:
  • the gutter/fascia materials delivered

CD68_BD32_110208_ax

  • minor overhang issue to the front left side of garage was fixed.

CD68_BD32_110208_fx

Sunday, February 10, 2008

Options we gave them to fix high doors issue

We emailed our CSR today re: our decision on the issue of high doors to the HT area.

We gave them 3 options and one of them is to give us a full credit for the two 2340mm high timber glazed doors to HT that they are going to replace with smaller 2040mm doors.

We hope to receive a response tomorrow.

Friday, February 8, 2008

Scaffolding and the rest of the windows

Calendar day 65 (working day 31):

They've set up the scaffolding in preparation for the installation of gutters/fascia on Monday:

CD65_BD31_080208_bbx

Window to the stairs (east-facing):
CD65_BD31_080208_xx
wonder what's the best way to cover this?

Sliding door to the dining area:
CD65_BD31_080208_qx

Using this,
CD65_BD31_080208_wx
DH went upstairs to take some photos (1st time):

One of the bedrooms to the rear of 1st floor (facing north) with a view of the new shopping centre currently being built just a few steps away:
CD65_BD31_080208_nx

Two of the bedrooms facing west have obscure-glazed windows (as required by the council, due to area facing the neighbours):
CD65_BD31_080208_mx

My Walk-in-Robe (WIR)... ooopppsss.. shall I say, 'Our' WIR ;)
CD65_BD31_080208_kx

Timber french doors to the master bedroom (exit to the balcony):
CD65_BD31_080208_jx

Preparation for fixing the overhang issue

The concreter went back today to start fixing the overhang issue:

portico area (one with the biggest overhang):
CD65_BD31_080208_ex


to the left side of the portico (front of mud room):
CD65_BD31_080208_gx

to the right side of the portico (front of Home Theatre room):
CD65_BD31_080208_fx

CD65_BD31_080208_hx

The concreter will come back on Monday to finish it; afterwards, we will inspect it with the site supervisor.

Thursday, February 7, 2008

We have the rest of the windows!

Calendar day 64 (working day 30):

We now have the timber doors and window to the master bedroom:
VCD64_BD30_070208_kx

side of the house facing the secondary street (east-facing):
CD64_BD30_070208_fx

trusses to the alfresco:
VCD64_BD30_070208_gx

west-facing area:
VCD64_BD30_070208_jx

Wednesday, February 6, 2008

We have windows!

We're still awaiting a response from our CSR re: the issue with the high doors.

In the meantime, we are making progres with our framing. We now have windows!

Calendar day 63 (working day 29):

Front door side lights and HT window (we also have a balcony now!):
CD63_BD29_060208_xx

windows to the ensuite:
CD63_BD29_060208_yx

east-facing windows to HT, kitchen and dining areas:
CD63_BD29_060208_ix

mud room window (looks really like a mud room...) :
CD63_BD29_060208_rx

family room:
CD63_BD29_060208_qx

bi-fold doors to family room going to the alfresco area:
CD63_BD29_060208_ox

laundry door frame only:
CD63_BD29_060208_sx

timber window for the upper floor master bedroom:
CD63_BD29_060208_ux