Friday, May 23, 2008

Cladding, Electrical, Plumbing...

Calendar day 170 (working day 102):

We have upper level cladding!!!!!!!!

front of the house:


and corner-turning side:




there were still some missing bricks near the kitchen window, as the window was changed to a smaller one (good thing SS realised that the window delivered and installed was the wrong size):


We noticed around 4-5 bricks above the front window to the HT were of different colours (a bit peachy.. we reckon they are Cotham):


Electricals were installed:

Meter box is to the side of the HT (but no HT cabling yet):


kitchen area:


bathroom:


and plumbing too:


We've been asking our CSR about our ple-plaster inspection date.. but looks like it won't happen soon.. wonder why. Kev said that pre-plaster inspection should be done as soon as the electricals are installed.