Monday, February 11, 2008

Building works stopped...

We were advised that building works has been stopped until the Home Theatre door issue is resolved.

When we visited the site in the afternoon, we saw:
  • the gutter/fascia materials delivered

CD68_BD32_110208_ax

  • minor overhang issue to the front left side of garage was fixed.

CD68_BD32_110208_fx

Sunday, February 10, 2008

Options we gave them to fix high doors issue

We emailed our CSR today re: our decision on the issue of high doors to the HT area.

We gave them 3 options and one of them is to give us a full credit for the two 2340mm high timber glazed doors to HT that they are going to replace with smaller 2040mm doors.

We hope to receive a response tomorrow.

Friday, February 8, 2008

Scaffolding and the rest of the windows

Calendar day 65 (working day 31):

They've set up the scaffolding in preparation for the installation of gutters/fascia on Monday:

CD65_BD31_080208_bbx

Window to the stairs (east-facing):
CD65_BD31_080208_xx
wonder what's the best way to cover this?

Sliding door to the dining area:
CD65_BD31_080208_qx

Using this,
CD65_BD31_080208_wx
DH went upstairs to take some photos (1st time):

One of the bedrooms to the rear of 1st floor (facing north) with a view of the new shopping centre currently being built just a few steps away:
CD65_BD31_080208_nx

Two of the bedrooms facing west have obscure-glazed windows (as required by the council, due to area facing the neighbours):
CD65_BD31_080208_mx

My Walk-in-Robe (WIR)... ooopppsss.. shall I say, 'Our' WIR ;)
CD65_BD31_080208_kx

Timber french doors to the master bedroom (exit to the balcony):
CD65_BD31_080208_jx

Preparation for fixing the overhang issue

The concreter went back today to start fixing the overhang issue:

portico area (one with the biggest overhang):
CD65_BD31_080208_ex


to the left side of the portico (front of mud room):
CD65_BD31_080208_gx

to the right side of the portico (front of Home Theatre room):
CD65_BD31_080208_fx

CD65_BD31_080208_hx

The concreter will come back on Monday to finish it; afterwards, we will inspect it with the site supervisor.

Thursday, February 7, 2008

We have the rest of the windows!

Calendar day 64 (working day 30):

We now have the timber doors and window to the master bedroom:
VCD64_BD30_070208_kx

side of the house facing the secondary street (east-facing):
CD64_BD30_070208_fx

trusses to the alfresco:
VCD64_BD30_070208_gx

west-facing area:
VCD64_BD30_070208_jx