We are at Fixing Stage!

Calendar Day 247 (Working Day 156):

We are officially at Fixing Stage!

The entry door to the Mud room has been installed.
Therefore, we could no longer enter the house!

Here is the clearest photo that we were able to take of the Kitchen area:



Laundry area:





Pergola timber slats were finally installed:





close-up look:


We're very pleased with how the pergola looks now.

Sunday, July 27, 2008

Plastering nearly finished!

Calendar Day 233 (Working Day 146):

We went to the house yesterday (Saturday) to see the progress, but saw some people cleaning the bricks!

Then we went back today and saw at least 3 people inside, cleaning the house!
Wow finally.. our house is being cleaned!
After our daughter's choir concert (around 4:30pm), we hurriedly went back to the house to take some photos.

Plastering is nearly finished!!!!!

HT (looks like these are the materials for the stairs):


Kitchen:


Fridge cavity & pantry:


Dining:


Leisure area (upstairs):


Ensuite:




Bathroom:


Bedroom 3's BIR:


Master Bedroom looking from the Leisure area:


and the only remaining area that is unfinished.. the garage:


Unfortunately, there's one wall that was accidentally hit by.. we reckon the cleaners:


Oh by the way, our SS rang Jerry last Friday to give some updates.
He said that he gave an instruction to the plasterers to do a good job, as the owners are very meticulous ;)

We reckon, they did a great work with the plastering!

Woohooo!!!!!

Friday, July 18, 2008

Plastering started!

Calendar day 226 (Working day 141):

More fixes were done this week.

Additional support to the floor joist:


Remember the wall to the Laundry that was cut to the top area, so our inspector asked for some support to the back?
SS initially said it was alright and won't be fixed, but now they fixed it!

They opened up the sisalation to the garage (back of Laundry) and put in some timber support to the upper wall.

HT cabling were installed:


and as per our SS, once the HT cabling is finished, plastering would commence.
They started with the bulkheads and other column walls:

HT entry:


Study entry:


Kitchen & Family:


Fridge cavity:


Ensuite:


Laundry:


and look at our kids...
they created some "mini pizzas" out of the timber shavings!
kids are really creative!

Friday, July 11, 2008

House feels warm and cozy - Insulation in!

Calendar Day 219 (Working Day 136):

Finally, the house feels warm and cozy.. coz the insulation is in!

Upstairs:


WIR:


Ensuite's shower:


Bathroom:


Bed 3:


some more Batts remaining:


Outstanding issues from the pre-plaster inspection:

Kitchen sisalation torn:


No support to cut laundry wall:


This one was fixed:


and.. plaster boards were delivered:

Friday, July 4, 2008

Pergola is finished!

Calendar Day 212 (Working Day 131):

Not a busy week for the tradies...
only the pergola had been finished this week:





the consolation is... we really liked it!
The quality was also superb!